Wednesday, June 16, 2010

Plumbing

The beautiful floor mounted shower in brushed nickel was ordered, the galvanized stock tank is ready to be picked up and the incredible stone sink is in the shop. All these parts should be here next week.

First attempt at keeping track of the adventures

First attempt at keeping track of the adventures

June 8, 2010 Jeff and I moved the container with the help of a truck that had a broken winch and used clever skills to get the thing on the truck. We mostly watched and directed traffic. Once the container was loaded, it was delivered to Big Blue within minutes and unloaded.


June 15, 2010 walked the roof of the container to assess the condition and found all metal and welds to be in good condition, recommended painting with two part epoxy paint. Approved

June 16, 2010 sprayed interior surfaces of container with standard garden sprayer, one gallon of water and 1 qt. of ammonia.